Window element for an exposed concrete wall / installation

  1. Both sides of the window blocks must be protected against dirt and damage during the concrete work. Cover plates with a thickness of 3 mm are sufficient. These are supplied by the manufacturer.
  2. The window(s) and formwork block(s) should be fixed between the formwork walls before the concrete is poured.
  3. A metal waterstop is placed in the middle of the concrete as a locking flange. This must be degreased and primed with quartz sand/epoxy resin. An injection hose must also be attached on site.
Window during production

Window during production

Window ready to be packaged and shipped

Window ready to be packaged and shipped

Styrofoam blocks for the shutter work

Styrofoam blocks for the shutter work

Testing the fit of the styrofoam block in the underwater window

Testing the fit of the styrofoam block in the underwater window

Window installed, concret poured, styrofoam block still in place

Window installed, concret poured, styrofoam block still in place

Finished installation with all 4 underwater windows

Finished installation with all 4 underwater windows